FGT Critical Notice

Notice ID: 74256
Notice Type: Planned Service Outage
Critical: Y
Notice Status Description: Initiate
Reqrd Rsp Desc: No Response Required
Posting Date/Time: Oct 21 2026 11:40 AM
Subject: NOVEMBER 2026 --- FGT WESTERN DIVISION AND MARKET AREA MAINTENANCE
Notice Effective Date/Time: Nov 1 2026 9:00 AM
Notice End Date/Time: Dec 1 2026 9:00 AM
Notice Text:

FGT will be performing maintenance between FGT Compressor Stations 4 and 6. This maintenance is scheduled to begin on November 2, 2026, and is to be completed by the end of gas day November 4, 2026. During this maintenance FGT may schedule up to 130,000 MMBtu/day through Stations 4 and 6. During normal operations, FGT schedules up to 230,000 MMBtu/day through Stations 4 and 300,000 MMBtu/day through Station 6.

FGT will be performing maintenance east of FGT Compressor Station 6. This maintenance is scheduled to begin on November 9, 2026, and is to be completed by the end of gas day November 27, 2026.

The first major receipt and delivery points west of the maintenance area available for nominations are:

Enbridge Orange Receipt (POI 78499)

Orange Entergy Delivery (POI 100811)

Golden Pass Receipt (POI 78503)

Golden Triangle Storage Receipt (POI 78523)

Golden Triangle Storage Delivery (POI 78524)

The first major delivery and receipt points east of the maintenance area available for nominations are:

Gillis-Trunkline Receipt (POI 100729)

Trunkline Manchester Receipt (POI 23059)

Egan Hub Receipt (POI 78299)

Egan Hub Delivery (POI 78300)

The following points in the maintenance area will be unavailable for flow:

Liberty Storage Receipt (POI 78448), Normal capacity = 400,000

Liberty Storage Delivery (POI 78450), Normal capacity = 400,000

Varibus Calcasieu Delivery (POI 10150), Normal capacity = 80,000

The above-described FGT pipeline maintenance in Zone 1 may require that all gas volumes scheduled at FGT delivery/receipt points west of the maintenance area to have corresponding volumes scheduled at FGT receipt/delivery points west of the maintenance area as well.

During this maintenance FGT may schedule zero volumes through Station 6 to points east of the maintenance area. During normal operations FGT schedules up to 300,000 MMBtu/day east through Station 6.

FGT will be performing maintenance at FGT Compressor Station 8. This maintenance is scheduled to begin on November 9, 2026, and is to be completed by the end of gas day November 20, 2026. During this maintenance FGT may schedule up to 850,000 MMBtu/day through Station 8. During normal operations, FGT schedules up to 1,098,000 MMBtu/day through Station 8.

FGT will be performing maintenance at FGT Compressor Station 9. This maintenance is scheduled to begin on November 5, 2026, and is to be completed by the end of gas day November 20, 2026. During this maintenance FGT may schedule up to 1,150,000 MMBtu/day through Station 9. During normal operations, FGT schedules up to 1,250,000 MMBtu/day through Station 9.

FGT will be performing maintenance downstream of FGT Compressor Station 10. This maintenance is scheduled to begin on November 5, 2026, and is to be completed by the end of gas day November 20, 2026. During this maintenance FGT may schedule up to 1,200,000 MMBtu/day through Station 10. During normal operations, FGT schedules up to 1,300,000 MMBtu/day through Station 10.

FGT will be performing maintenance downstream of FGT Compressor Station 11. This maintenance is scheduled to begin on November 2, 2026, and is to be completed by the end of gas day November 20, 2026. During this maintenance FGT may schedule up to 2,800,000 MMBtu/day through Station 11. During normal operations, FGT schedules up to 3,250,000 MMBtu/day through Station 11.